Project Overview

  • Case Study: EMS Adds to Existing Stores
  • Technology: Energy Management Systems
  • Market: Specialty Retail – Discount Stores
  • Project Duration: 2 Months
  • Number of Locations: 20

Customer Challenge

A nationwide discount retailer in the US chose to add EMS systems and test the systems’ impact at a select group of stores. As a longtime partner in New Store Openings (cabling, POS, network, etc), Worldlink was selected to install this equipment as part of the test.

Worldlink Solution

  • Coordination of activities with Retailer and EMS Partner
  • inventory management of all equipment
  • equipment staging and kitting
  • equipment installation testing, and turn-up
  • commissioning of system